“A customer asked for something new. How do I price it?” Carefully, and less blindly than it feels. A job you have never done is rarely new from top to bottom. Most of it is work you price every week, plus one or two steps you have not done before. The method is to price the familiar parts the way you always do and put your effort into the new parts. Read how the product is meant to go in, check your hours against a published cost book, and charge for the learning. Then decide whether to take it at all.
The example running through this article: say a siding contractor who has installed vinyl for years is asked to re-side a house with fiber-cement lap siding, about 1,800 square feet of wall. The figures in it are illustrations, not real rates.
Step 1: split it into tasks, and mark the new ones
Write the job out the way the crew will do it, in order, and mark each step as one you know or one you do not.
| Task | Known or new | Where the number comes from |
|---|---|---|
| Tear-off and disposal | Known | Your own vinyl jobs |
| Sheathing repair, housewrap, flashing | Mostly known | Your jobs, checked against the maker’s details |
| Trim | Partly new | The maker says not to use the lap siding as fascia or trim, so it is a separate product |
| Cutting and installing the lap siding | New | The installation instructions, a cost book, a learning allowance |
| Caulk and paint | New, or subcontracted | A painter’s price, or the maker’s finish rules |
| Dust control and clean-up | New method | The instructions and OSHA’s silica rule |
Two of the six tasks are familiar work and a third is partly so. The new risk sits in the other three, so that is where the time goes.
Step 2: read the installation instructions before you price
The manufacturer’s installation instructions are a free estimating tool, and they are where the hidden costs live. The September 2019 edition of James Hardie’s HardiePlank instructions opens with a warning in capitals: failure to follow the company’s written installation instructions and the building codes “MAY AFFECT WARRANTY COVERAGE.” Get the current edition before you price, because the instructions themselves tell you to confirm you are using the correct HardieZone product instructions. Read it with a pencil. Every rule in it is time or material:
Do the same with any new product: the window, the tub surround, the composite decking. If you cannot find the instructions, or they are vague, count that as a risk too.
Step 3: check your hours against a cost book
Your own hours are the best data you have, and for the new task you have none. A published cost database gives you a second opinion. Gordian’s RSMeans is one. Its 2026 Residential Costs book is described as “aimed at estimating the cost of new residential construction,” and its Contractor’s Pricing Guide covers “the most common repair and remodeling projects costing between $10,000 and $100,000.”
The useful column for a first job is labor, not dollars. RSMeans explains it this way:
Use the book as a check, not as your price. Say your own breakdown of the new siding task comes to 90 crew-hours. Multiply the book’s labor-hours for the matching line by the house’s quantity. If the book says much more than 90, believe the book until a job of your own proves otherwise. If it says much less, ask what you are counting that it does not, such as a hilly lot, three stories or a lot of trim.
Step 4: put your own costs on the hours
Once you have hours, price them the way you price everything else. Use your burdened labor cost, then your overhead per billable hour, then your markup. For a hired hand, the Bureau of Labor Statistics put the median carpenter’s pay at $29.12 an hour in May 2025, and your cost is more than the wage. Work it out in Your Real Hourly Cost, then add overhead with Overhead per Billable Hour and a markup that gives the margin you need, as in Markup vs. Margin. New tools bought for this job go in at cost. If you will use them again, spread them over the jobs you expect.
Step 5: charge for the learning
The first time takes longer: reading the instructions on site, a cut done twice, a call to the supplier. That time is real, and it belongs in the price of the first job, not in your evenings. There is no standard figure. Pick an allowance you can defend and put it on the new tasks only. For example, 25 percent on the 90 crew-hours adds 22.5 hours. The tear-off and the housewrap get no allowance, because you know them.
Then widen the range you quote. At first contact, give a range rather than a single number, and set the fixed price only after the site visit. Price the true unknowns separately, such as rotten sheathing behind the old siding, at a stated price per sheet. Remodeling Contracts: Fixed Price, Cost-Plus and Allowances covers those forms. A familiar option next to the new one also helps the customer choose: quote vinyl and fiber cement side by side, as in Good, Better, Best.
Step 6: decide whether to take it
Some new jobs are worth learning. Others are better sent to someone who already does them. Say no, or subcontract the part you cannot do (see Marking Up Subcontractor Work), when:
After the job: write down what it really took
The first job buys you the data the second job needs. Log the actual hours by task next to the estimate, and note what the instructions or the cost book got right. Job Costing shows a simple way. By the third job the allowance should be gone and the range narrower. That is also the time to show the new service’s price on your website. NapkinPrice™ puts an instant price range from your own pricing rules on your site, so add the new service once a few real jobs have shown you its numbers.
General information, not legal or tax advice. Rules change and vary by state; check with the agency named above or a professional for your situation.